Urgent Maintenance MED1 facility network maintenance

Thursday, 28 November 7 hours
Complete
Complete

eliminated stp loops, disconnected old switches from network.

Avatar for Dmitry Sherman
Dmitry Sherman
Underway

migrated all customers and ports from cisco 4500-x vss pair to new Arista 7280sr3.

Avatar for Dmitry Sherman
Dmitry Sherman
Underway

The scheduled maintenance is now underway. We'll keep you updated on our progress.

Avatar for Dmitry Sherman
Dmitry Sherman
Scheduled

job will have to be postponed, we need to do some more preparations. We will issue this job as soon as possible.

Avatar for Dmitry Sherman
Dmitry Sherman
Scheduled

Dear Team,

We are conducting urgent maintenance at our datacenter to address a recent issue. This maintenance is necessary to ensure continued system reliability and performance.

Expected Downtime: Up to 2 minutes per interface We aim to minimize disruption and complete the maintenance promptly. Please reach out if you have any concerns or require further assistance.

Thank you for your understanding and cooperation.

Avatar for
Began at:

Affected components
  • Tel Aviv MED1
    • PARTNER CORE 1 (ISP)
    • PARTNER CORE 2 (ISP)
    • TAMARES TELECOM (ISP)
    • IIX Global (ISP)
    • DARKFIBER 1 (ISP)
    • VM CLUSTER