Dear Customer,

We would like to inform you about a planned work scheduled in Shacham Tech Datacenter.

PW Reference Number: 46580 Location: SHACHAM 40 Datacenter

Maintenance Window: Start date/time: 27/07/2025 21:00 UTC End date/time: 28/07/2025 03:00 UTC

Scope of work: Moving the Layer3 of the communications from Aggregation Machine to a new Router. Impact: 5–30 minutes of expected downtime.

If you have any further inquiries regarding this work, please do not hesitate to contact us.

Always at your service, Interhost.

Avatar for Ariel Domchik
Ariel Domchik
Began at:

Affected components
  • Tel Aviv HaShacham
    • BEZEQINT (ISP)
    • BEZEQINT-NG (ISP)
    • DARKFIBER 2 (ISP)
    • VM CLUSTER
    • core switch l3 - ar-sh7280-1
    • core switch l3 - ar-sh7280-2
    • Nyon (ISP)