Dear Customer,

We would like to inform you about a planned work scheduled in Shacham Tech Data Center

PW Reference Number: 46905 Location: Shacham 40 Petach Tikva

Maintenance Window: Start date/time: 10-09-2025 20:00 UTC End date /time: 11-09-2025 03:00 UTC

Scope of work: Yearly Preventive Maintenance of Generator G3. Impact: No downtime expected. MOP: Generator G3 will not backup during the Maintenance.