Dear Customer, We would like to inform you about a planned work scheduled in Shacham Tech Data Center.

PW Reference Number: 50290 Location: Shacham 40 Petach Tikva

Maintenance Window: Start date/time: 29-04-2026 20:00 UTC End date /time: 30-04-2026 03:00 UTC

Scope of work: Transformer units 3, 4, 5 Protection Systems Upgrade.

Impact: No downtime expected

MOP: Transferring all the Electrical load to Generators and replacing the Units.

Generators Backup will be active during the Maintenance. Electric Company Power will not be available during the Maintenance.

If you have any further inquiries regarding this work, please do not hesitate to contact us.

Always at your service, Interhost.