Dear Customer,

We would like to inform you about a planned maintenance work scheduled in Bezeq International Tech Data Center.

PW Reference Number: 44747
Location: Data Center Shacham 40 Petah Tikva

Maintenance Window: Start date/time: 17-11-2024 06:00 AM UTC End date/time: 21-11-2024 14:00 PM UTC

Scope of Work: Maintenance to Chiller 1-7
Impact: No downtime expected.